21.12.11. A wet and miserable day, but we got on with cutting pieces of steel to make up the wall of piles on the road side of the slip. When done we'll weld them in place.
You can also see from the photographs that the protective hoses are now in place to get water and electricity to the other side of the slip and all connected up. The pump out hose has also been connected and put into position.
Next job will be to wacker the hardcore, position the reinforcement and pour the concrete to complete this part of the work.