26.8.11. A very wet day, rain almost all day with downpours at the most inconvenient times, so all the full team was soaked with rain and the concrete team was soaked in concrete too, which became very sloppy. A very difficult job to deal with. All attending worked like Trojans, the concrete team and the digging team doing a mechanical digger's job by hand with pickaxe and shovels as it was inaccessible with the digger. This completes the 3rd and 4th bays, leaving the last to be done next week.