31.8.11. The hardcore and re-enforcing work has been done for the 5th of the bays on the actual slipway, ready for the pouring of the concrete this Friday. When cured enough we can start work on the apron to the slip, which will extend the new slip beyond the length of the old one, It will also make it deeper by two feet.