1.5.12.  Luckily a dry day for the final concreting job. The final length of the road side of the slip as it was a small pour was done on the day before as was the bottom picture of this post.
Today's was a full load of the concrete mixer lorry with the conveyor belt and went into the water side of the slip wall, and the end of the jetty and steps. Most of the usual helpers, led by Colin, were there, and though we found the load to be just not enough to fill Ashley's shuttering, Alan was able to get another small load in time to complete the job without a stoppage.
     