5.1.12. A very cold and windy day, with the usual four suspects worked on preparing for concreting at the top of the slip. It will be quite complicated in that it will have the first two lengths of the track, two layers of reinforcement, another two lengths of reinforcement made into box sections and the concrete, all to be done in the right sequence. Today was wackering the hardcore and positioning the first section of reinforcement and encasing the tubes carrying electrics, water and sewage, in sand and positioning them under the reinforcement. But before we can get to the actual concreting we have to finish off the pile wall that will be under the track next to the roadside.