5.12.11.  Today's work is on the top of the slip, cutting the concrete there prior to digging it out tomorrow. We need to re-connect the tube from the pump that had been cut. Also position a cable to fit a street light on the other side of the slip. Then dig out so as to place the first of the tracks that have been painted by Charlie on the pads welded on the frames, by Dennis and John and S.
The other photographs here are of the new carpark area and the jetty from the fuel tank to the carpark, at least the preparitory work.