8th of July and we're working on the next two blocks, B and C. We'll pour them from the same load of concrete, cheaper that way.
The concrete is poured into formers, of which we have made two, fastened to steel plates welded to the piles, so they become integral with the piles. Positioning the blocks at the right height is critical of course, to maintain a suitable slope.