23rd of June and we have dug the area for the first concrete block, the one furtherest from land, block "A", it carries frame A. All the frames have been welded up previously and have stood on the hard standing for weeks.

These photographs show the former being put in position with re-enforcment in place. The next step is to pour the concrete into it.
 